Shotcrete fiber

Fewer metres of mesh, more metres of tunnel per shift

In sprayed support the binding constraint is rarely material cost — it is cycle time. Less mesh handling, faster support cycles and a smaller crew turn straight into advance rate.

The expensive problem

Fixing mesh is the slowest part of the cycle

It is also the part that keeps people under freshly exposed ground for longest.

  • Mesh sheets cut and bent to a profile that is never quite regular
  • Crews working at height under partially supported ground
  • Rebound trapped behind the mesh, wasting sprayed material
  • Shadowing behind the bars, leaving voids in the lining
  • Every fixing hour is an hour the face is not advancing
  • Plant and crew standing while the support cycle catches up
Cutaway model of a fiber-reinforced shotcrete tunnel lining

The Polyguard solution

ShotGuard PG SC-48, dosed in the sprayed mix

ShotGuard is shaped and sized to pump and spray cleanly, with low rebound and no blocking at the nozzle. The reinforcement arrives with the concrete, follows the excavated profile exactly, and takes the fixing operation off the critical path.

Grade
PG SC-48
Fiber length
48 mm
Typical dosage
4–9 kg/m³
Application
Wet and dry spray

What comes off the cycle

Operations that leave the critical path

  • Mesh cutting, lifting, positioning and fixing
  • Working platforms and access set up purely for fixing
  • Rebound losses caused by spraying through a mesh curtain
  • Void and shadowing rework behind bars
  • Crew and equipment standing time between spray passes
  • Exposure time under freshly excavated ground

Cost per linear metre

The right unit is metres of tunnel

Price per kilogram of fiber tells you nothing about a tunnel. Divide the whole support package — steel, fixing labour, crew and plant time — by the metres it delivers, and the comparison becomes decidable.

The calculator below converts everything to a saving per linear metre and a total for the drive.
Mesh support, installedSteel + fixing + standing time
SteelTransportCutting & lapsChairsLabourSupervisionDelay
ShotGuard, dosedFiber in the sprayed mix
FiberDosing

Steel purchaseTransport & storageCutting & lap wasteChairs & spacersPlacing labourSupervisionPlacement delayPolyguard fiber, dosed in the mix

Proportions are illustrative. Fixing rates vary widely with ground class and profile.

Two horizons

Programme now, durability later

During the drive

  • Support cycle shortened — more advance per shift
  • Smaller crew at the face, less time under exposed ground
  • Lower rebound, so less sprayed material wasted
  • No mesh delivery, storage or cutting logistics

In service

  • No corroding steel in a wet, chloride-bearing lining
  • Reinforcement that follows the profile with no shadow voids
  • Fewer local repairs to a lining that is hard to access
  • Micro fiber can be added where fire spalling is a design case

Worked example — 1,200 m drive, 18 m sprayed perimeter

Illustrative rates. Replace every figure with your own in the calculator below.

Sprayed area
1,200 m × 18 m = 21,600 m²
Lining
120 mm → 2,592 m³
Mesh at 3.0 kg/m², 0.95 /kg
≈ 61,560
Fixing at 2.40 /m²
51,840
Fixing time at 4 min/m²
1,440 crew-hours
Crew & plant at 85 /hour
122,400
ShotGuard at 6 kg/m³, 3.60 /kg
≈ 55,987
Saving per linear metre
≈ 149.8 /m

The fixing hours are the headline. Removing 1,440 crew-hours from the critical path is worth more on most drives than the steel it replaces.

Your numbers

Shotcrete & tunnel calculator

Set your own ground-class fixing rate and crew cost. The output is expressed per linear metre so it can go straight into a tender comparison.

Shotcrete & tunnel calculator

Cost and cycle time per linear metre of tunnel.

CurrencyUSD

The excavation

Welded mesh support

Polyguard ShotGuard

Result

Sprayed area
—
Shotcrete volume
—
Steel avoided
—
Mesh, installed
—
Mesh-fixing hours removed
—
Crew & equipment time
—
Polyguard, dosed
—
Saving per linear metre
—
Total project saving
—

Indicative only. Fixing rates and crew costs vary with ground class, profile and method. Confirm the dosage by design and a site trial.

Questions engineers ask

Spray, dosage and acceptance

Wet or dry process?
Both. Dosage and mixing sequence differ, and we supply the sequence with the recommendation.
How is performance demonstrated?
Through residual strength testing on panels or beams from your own mix, to the standard named in your specification. We support the trial and the sampling.
What happens to rebound?
Spraying through a mesh curtain traps rebound behind the bars. Removing the mesh removes that mechanism; actual rebound still depends on nozzle technique, mix and profile.
Can it be combined with lattice girders?
Yes. Fiber can replace the mesh layer where the performance-based design permits; the primary support elements remain as the designer has specified them.

Price the whole shotcrete cycle, not just the mesh

Send the drawing, the exposure class and the loading. You get a dosage recommendation, a data sheet and an installed-cost comparison against your current specification.

Speak to a fiber engineer

Technical desk

Send this result to an engineer

Your calculation is attached to this enquiry automatically. Add your name and email — and a note of your own, if you want one.

See what gets sent