Products Polypropylene concrete fiber Macro synthetic fiber Buy concrete fiber Applications Calculators About us Technical notes Contact Request a quote

Industrial flooring fiber

Reduce total reinforcement cost, not just the steel invoice

Compare the total installed cost of conventional reinforcement — not just the price of steel — with the Polyguard fiber solution.

The expensive problem

A mesh layer costs far more than the mesh

By the time a mesh layer is in the slab it has collected seven other cost lines, and the project pays every one of them.

  • Steel purchase, priced per kilo but ordered with lap and cutting waste
  • Transport to site and the yard space to store it
  • Cutting, bending and offcuts that leave as scrap
  • Chairs, spacers and tying wire, plus the labour to set them
  • A fixing crew whose day is not spent placing concrete
  • Supervision and cover checks before the pour is released
  • Pours that wait for the steel to be signed off
Cutaway of a fiber-reinforced concrete floor slab

The Polyguard solution

Structural macro fiber, dosed in the batch

Embossed macro polypropylene filaments are dosed by kg/m³ at the batching plant and dispersed through the whole section. Once a crack forms the fibers bridge it and carry load across it — the mechanism that lets a designed dose take the place of a crack-control mesh where the engineering design permits.

Grade
PG MF-54
Fiber length
54 mm
Typical dosage
3–7 kg/m³
Crack control
Three-dimensional

What comes off the bill

Cost lines that stop existing

Where the design permits mesh removal, these leave the programme as well as the budget.

  • Steel purchase and the waste allowance on top of it
  • Transport, offloading and yard storage
  • Cutting and bending on site
  • Chairs, spacers and tying wire
  • Mesh-placing labour and the supervision that checks it
  • Programme float lost waiting for reinforcement sign-off
  • Long-term repair of corrosion-driven cracking and spalling

The comparison that matters

Installed cost, side by side

Set the two bars against each other with your own rates. On many projects the steel purchase is only one component of the installed reinforcement cost. Accessories, fixing labour, logistics, waste and programme effects carry the rest, and together they move the final cost per square metre more than the steel invoice does.

The fiber bar is a single line item: kilograms dosed into concrete you were pouring anyway.
Mesh, installedSteel + everything attached to it
SteelTransportCutting & lapsChairsLabourSupervisionDelay
Polyguard PG MF-54Fiber, dosed
FiberDosing

Steel purchaseTransport & storageCutting & lap wasteChairs & spacersPlacing labourSupervisionPlacement delayPolyguard fiber, dosed in the mix

Proportions are illustrative. The calculator below uses your figures instead.

Two horizons

Saved on day one, saved for twenty years

Day one

  • Steel, accessories and fixing labour removed from the bill
  • Pours released sooner — no reinforcement inspection queue
  • Smaller site crew, less lifting and handling
  • Fewer deliveries and less yard congestion

Over the service life

  • No corrosion, so no rust staining or spalled cover to repair
  • Crack control through the section, not just at mid-depth
  • Fewer joint and surface repairs interrupting operations
  • Downtime avoided in a building that has to keep running

Worked example — 5,000 m² warehouse slab

Illustrative rates. Replace every figure with your own in the calculator below.

Slab
5,000 m² × 180 mm = 900 m³
Mesh
3.9 kg/m² + 12% lap waste
Steel at 0.90 /kg
≈ 19,650
Chairs & spacers at 0.35 /m²
1,750
Placing labour at 1.60 /m²
8,000
Conventional, installed
≈ 29,400
Polyguard at 4 kg/m³, 3.40 /kg
≈ 12,240
Direct saving
≈ 17,160 · ≈ 3.43 /m²

The steel line is 19,650 of a 29,400 package. Even if steel were free, the remaining 9,750 would still be on the job — which is why the comparison has to be made on installed cost.

Your numbers

Industrial flooring savings calculator

Every input is yours. Nothing is pre-loaded with a Polyguard assumption except the dosage range, and that is set by design.

Industrial flooring savings calculator

Total installed reinforcement cost against a fiber dose.

CurrencyUSD

The slab

Conventional reinforcement

Polyguard

Result

Concrete volume
—
Steel avoided
—
Steel purchase
—
Chairs & spacers
—
Placing labour
—
Conventional, installed
—
Fiber required
—
Polyguard, dosed
—
Saving per m²
—
Saving on reinforcement
—
Direct saving
—

Indicative only. The dosage must be confirmed by structural design and a trial mix; removing mesh is valid only where the engineering design permits it.

Questions engineers ask

Specification and site

Does removing mesh change the joint layout?
It can. Fiber gives three-dimensional crack control, which usually allows wider joint spacing than an equivalent mesh layer — but joint layout stays a design decision based on traffic, sub-base and the shrinkage regime.
How is the fiber added?
At the batching plant, by weight, with the mixing sequence we supply. No change to placing equipment and no change to the power-float sequence.
What does it do to the surface finish?
At the specified dosage, nothing a normal power-float sequence does not handle. We attend the first pour if you would like the crew shown once.
What documentation do I get?
Technical data sheet, safety data sheet, batch quality record and a written dosage recommendation against your mix. Test reports on request.

Price the whole slab reinforcement package, not the steel

Send the drawing, the exposure class and the loading. You get a dosage recommendation, a data sheet and an installed-cost comparison against your current specification.

Speak to a fiber engineer

Technical desk

Send this result to an engineer

Your calculation is attached to this enquiry automatically. Add your name and email — and a note of your own, if you want one.

See what gets sent